Final planks

The final plank went on easy – seemed simple enough to sand it all flat, apply a crap load of resin and screw it down, being careful to avoid air pockets (propping up one end and working towards it screwing it down along each ‘row’ of screws ensured that no air was trapped). I managed to get back to the shed in time to remove all the screws (about 200 i think) before the resin was super solid this time, so no soldering iron needed (which was a relief with that many to remove!).

Once set i hacked the edges relatively flush with the power planer on its deepest setting then belt sanded it flush. The planer is a critical tool along with the belt sander i think. Without these its all possible of course, but i reckon doing this with unpowered tools might take between 3-5 times longer. The investment in tools vs the cost of renting the shed space for longer actually makes the result about a net zero i think (and its a lot less boring).

I stuck the stem cap on and shaped it. I diverged from the kit a bit here (although its not entirely clear what is intended in the kit unless I’m missing something – which i probably am given the rest of it looks good so far). I filled the knee with a piece of hard wood to almost its lowest point, and then shaped what i thought looked best and closest to the plans from Janusz.

When waiting for resin to set (and i was actually supposed to be working hard during the day – the joys of working from home at the moment mean some long lunch breaks…) I was able to make a couple of things i needed for the glassing step. With a pregnant wife and small toddler, and a current local lockdown I’m doing all the build completely alone. To make things easier for this shorthanded approach I made some mixing paddles for the drill out of some stainless rod i had in the garage, and a fibreglass roll holder to make cutting the required lengths managable.

Radio Silence

So I’ve been a bit busy lately. But boat works continued… The next three posts are my progress to date. And boy has it been fun!

Hull planking is completed. The panels fitted pretty good, they needed some trimming, and the bow panels were a bit of a mission to force into place (i used a ratchet strap eventually). Lots of trimming, re-ratchetting, marking, trimming, ratchetting etc… But eventually they were in.

Felt pretty good to get that done to be honest.

I then started thinking about the fibreglassing step – so made a sample in the garage, with a radius to see the drape of the cloth and the overall amount of resin required for a given area.

I’ve chosen a heavy biaxial +-45 degree, medium twill (good drape), and a very thin top cloth – which adds up to just over the required weight per square metre. The biaxial provides torsional stiffness, the woven layers a reasonable resistance to hogging (as if the boat needs any more strength – may as well make the glass do something useful though!).

The cross section of the sample looked good, almost exactly 1mm thick and relatively easy to wet out etc. The peel ply finish looked good, bobbly without sanding and no amine blush. Well worth the cost hopefully.

In the mean time Alex has been worried about his weight. Not much help at all in the workshop.

See what I mean about Alex? We’ve all been there mate. Mr Thompson blames his helmet though – it does seem pretty heavy to be fair.

Unsticking stuck stuff.

Because i’m a chump, I placed the screws that pull down the edge of the bottom sheet of ply too close to the edge to allow me to plane it flush with the angle on the stringer. So i needed to remove them. I tried using an impact driver – and immediately tore the head off the first one. I tried the drill as a screwdriver – much gentler – but still tore the head off the next one. and the next one, and the next. The 5th came out clean, but the 6th and 7th – no joy.

Clearly the epoxy is doing its stuff. To be able to take the wood around these broken screws down to the right angle i used the belt sander and simply sanded the remaining bit of screw down with the rest of the wood, but i needed a better solution as this took ages and felt like a bit of a bodge. Out with the chicken Gougeon brothers book.

Sure enough they recommend using a soldering iron to heat the head of the screw and while the epoxy is soft from the heat, unscrewing it as normal.

I dug out the most powerful soldering iron i could find and flipped the point around to provide the biggest surface area to the screwhead. (in hindsight filing it down to a pozi drive shape would have been even better).

I was amazed. I held the iron on the screwhead for a count of about 45 seconds, then simply undid them – only one sheared off and this may have been due to not doing the full 45 seconds, or a bad heat connection between the iron and screwhead.

Chalk up yet another uber-win for the Gougeon boys.

I was then able to quickly power-plane down the wood to the correct shape ready for the final planking task. Early finish – back home in time for a Downton. Lovely.

Hull plating in the cow shed

Progress recently has been slow – other stuff and illness (not Corona – just a heavy cold I think/hope) has been keeping me away from the shed.

I managed to get some hull planking done (plating maybe – as the panels are flat? – meh). The process of popping all the panels out of the sheets took a suprisingly long time. Even with a 22’x 11′ work space there isn’t really any room for stacking the sheets flat so i made an upright stand thing that holds the sheets on their 4′ edges, this means that to get to the back of the pile i have to take off all the sheets in front and stack them separately, rather than be able to slide them out sideways. Anyway, after a couple of hours of shed time I had all the 18 panels and corresponding butt blocks cut out.

I thought i had enough clamps to position all 6 topside panels on the boat to check for fairness and symmetry of the structure, but ran out well short of even one side of the boat. A quick trip to the Foolstation and i picked up some giant clothespeg clamps that have proved to be worth every penny. At a measly 87 pence each these are by far one of the best purchases i have ever made at that slightly dubious tool vendor. (to be fair, their stock availability is usually amazing and they’ve got me out of a few scrapes in the past, its just that the quailty of the tools they sell is usually second only from the bottom of the heap to the total mixed bag that is Amazon’s selection).

The dry fit went well, with some minor adjustments to the bevelling with the sander. I then screwed the bottom and top edges of the panel to the stringers where i could see what i was screwing into. Once attached i drew around all the internal items touching the panel so i knew where to add additional holes for the bits that i couldn’t see. The panel was then taken off, and the holes added to the panel on the bench (or rather the random gate-legged table i seem to have inherited with the workspace). Then it was re-attached to the structure, using the originally drilled screw holes and using the holes just drilled on the bench holes were rebored through the stringers and frames in the areas that i couldn’t see previously and the countersink added on the outside. The end result is a panel with the areas that require glue to be applied drawn on, and the screw holes all pre located accurately, meaning the jobs that are required when gluing are limited to simply doing the saturation coat on both stringers and frames and the panel itself, adding the 406 filler then overcoating with this adhesive mix on the panel, offering up and screwing down, using the pre-drilled screw holes to locate it precisely – in this way i was able to do 6 panels per session in the shed which equals efficiency with the glue, and also time.

When doing the bottom panels I realised that I hadn’t added the stiffener piece #6 (i think it was) to the slot in the bunk sides before gluing on the stringers… so, given i couldn’t move the stringers or the bunk sides i was left with only one option to add it back in, and that was to cut a bigger slot in the bunk side (about 20mm long) to slide it into place. I’ll fill this once the hull is turned. It could have been a lot worse, so happy that so far this is the only fail in my planning…

Once i’d glued these panels on i reviewed the B&B video and they actually recommend doing the topsides planking, then the chine, then the bottom… slightly panicking that i’d made a huge balls up by doing topsides and bottom first, i did some quick checks and i’m going to end up with the same result in the end. I’ll just be bevelling the bottom plank to accept the chine plank, whereas the B&B version involved trimming the chine plank to meet the bottom plank – which might be a bit easier. I’m 99% sure there is enough material on the chine plank to do this… that 1% is still a bit worrying though.

In other news – i’ve moved to 100% West System products for laminating and gluing. The couple of issues i had with the PEC resin was probably user error, but i’m not going to risk anything else for now. I’ll use it up on the interior coating stage. I’ve used West resins a fair amount previously and they have literally never failed, even in my incapable hands. The resin seems to be really fault-tolerant given i accidentally mixed in about 30% more hardener than necessary to one batch of resin and it still cured fine… Not that i want to repeat that.

I use a measurement of resin to hardener by weight all the time, the pumps always appear to be inaccurate, especially on small quantities such as in gluing jobs. Keeping the scales in a clear zip lock bag at all times is working wonders for their service life…

I also bought a fair amount of 406 filler for gluing purposes, the website had a disproportionately small price leap from the medium bucket of filler to the large one. But i’m pretty sure i’ve now got enough for a number of boat builds…

Bevelage

Started on the beveling yesterday night. This was a job that i wasn’t particularly looking forward to, as it seemed to require resolving many angles and planes and intersections while simultaneously wielding power tools and taking chunks out of the hard won structure built thus far.

However after some timid and tentative investigations involving making bits of scrap wood into sawdust I decided that the correct tools for the job were an old Wickes branded belt sander that has had little use other than to make a laminated rudder for adapting an inflatable canoe to sail about 15 years ago and has been getting in the way everytime i moved house since, a powered plane (cordless – which i’ve come to realise is a feature of power tools that is incredibly useful when boat building) and a hand plane (also Wickes brand – but sharpened to within an inch of my whetsone’s life). Also into the mix came a couple of long straight edges (metre rules), a mask, snorkel and ear defenders with some music piped in via ear buds completed the tool list.

I started at the aft end of the boat where the angles are simplest (i.e. most obvious) – using the electric planer to take off most of the material from the length of the stringer in big sweeps down its length, then doing the frame edges to the ‘rocker’ with the sander (the planer takes chunks out of the plywood gussets if not careful) and then going back to the intersections of the stringers and frames to get those 100% right before going back to the rest of the stringers inbetween the completed frame intersections and using the planer, the sander and the hand plane to get it all right along the full length of the stringer. The straight edges were constantly in use every few minutes being placed between the stringers to indicate where the panels would sit to get the angles just right. Pretty sure that description made very little sense. If i remember I will take some intermediate photos of the process when i’m next at the shed…

The result has been ok so far. There is still some final finishing that needs doing on the one and a half completed stringers i did last night in about 2.5 hours. Some wibbles in the intersection of the angles along the stringer length are still obvious and need taking down towards the bow of the boat where the angles get a bit more complicated, but i reckon i’m 90% of the way there with that one.

For a job that i was fearing, this one has actually started pretty well. Just need to get on with it now.

In the photos below there are some really weird optical illusions – i promise you that the angles are actually correct! One of the photos has a bit of stringer in it that looks completely out, but is actually right… I think.

Edge-set and epoxy

I’ll not pretend that fitting the stringers has been a particularly fun job. The sheer clamp and mid-panel ones went in fine, the chine one however… the cow shed probably hasn’t seen that kind of language since the late Miss Daisy ate the farmer’s new iphone back in 2010 and it had to be surgically removed from one of her stomachs by the local vet.

The edge set (bending the way the stringer doesn’t want to bend – i.e. in a bow along the 50mm dimension) meant that the forces involved were pretty high. Lots of clamps, and lots of marking, cutting and recutting, and remarking and recutting of the notches in the oak floors eventually got a good fit, but at the expense of one clamp that literally fell apart in my hands and some new grey hairs. Not 100% sure that adding the oak floors at this point was really the best route to take. It just adds more notches that have to line up at this stage. Still, its done now, and looks and feels very solid. The stem joins aren’t quite finished yet, one stringer is slightly too high in the photos and the chine stringer to knee joint still needs finishing and attaching permanantly.

A learning point for me was that the notching for the forward frames needs to be so deep that the placement of the screws when building the frames should have taken this into account. I got very close to the screws in their pockets on the forward two frames. Ideally i should have moved the screw locations in by 10mm and had them off the centre line of the frame timber, or simply not kept the screws in when making the frames, and backed them out once the epoxy had set – leaving no hardware in the joint.

In other news, I previously mentioned that the ‘microfibres’ that Fyne provided were similar to 406 filler from West System. This is not the case, the microfibres are milled cotton I think, and 406 is collodal silica so have not got the same mechanical properties. All the joints I’ve made with both have been successful apart from the scarf, which i attribute to the resin gettting slightly crystalline in the pumps. I’m moving to 406 for all adhesive tasks in the future, with the microfibres being used with wood flour for fillets.

One disadvantage of working the shed of an evening is the lack of, ah, facilities. Using the materials I had to hand at the time, I now know the exact capacity of my bladder.

Next job is bevelling of the stringers and frames to take the hull planking. To allow for my own incompetence I’ve already ordered some spare blades for the electric planer, as it will only be a case of when, not if, I hit any screws that are not buried deep enough in the stringers…

Buenos Notches.

This week has been all about stringers and notching the frames accurately. The pre-formed notches are the minimum sizes, but need bevelling before a nice tight fit on the stringers and the stringers need sinking into the frames at the bow where the frame itself will lose a lot of material during the frame bevel process before planking.

Not much to say about this process, just some clamping, aligning, re-aligning and rasping (with a thin wood rasp) and sanding with a custom block that fits the notch has allowed some reasonable progress on this. Oh, and more rechecking of dimensions before drilling, countersinking and screwing the stringer in place.

I discovered that one side of the hull was 25mm longer than the other – almost identical to Pete B’s experience, and found (after much head scratching) that the stem wasn’t vertical and the transom pulled slightly out of true… Once i corrected this, the hull sides (stringer lengths) are within a few mm. Also i corrected minor bulkhead/frame location discrepancies between the sides, simply measuring the distance to each as I went along the hull before i screwed the stringers into place.

To avoid the whole assembly warping as i worked (the stringers sometimes require quite a lot of force to get them into position, so try to pull the frames out of line when released) i clamped and screwed the stringers in sequence, working on the same stringer on each side (i.e the upper chine one first) and working from the notch on the transom starboard side, the port, then the next frame on starboard, then port etc until i reached the bow. Basically trying to keep forces opposed to each other equal as i went along. Not sure how necessary it was, but it seems to have worked out ok.

The stringer assembly is now dry fitted apart from the top (bottom chine) stringer – the sheer clamps were in place before these photos were taken, but i came back to the shed one night and found both scarf joints had failed! I tracked the cause down to having used some resin with crystals in it. The damp in the shed and changes in temperatures during the thundery weather recently has affected the resin in the pump units on the cans and i must have used this in the mix. The epoxy had penetrated the wood fine, but the joint in the middle glue-to-glue had failed leaving a white powder or bloom in the joint. Fresh resin after rasping then sanding off the old stuff thoroughly seems to have worked, but I’m glad to have found this in such a small joint, having a large batch being affected (say, during planking) would have been much more difficult to deal with. I now know what to look out for. Once the new resin has had a chance to cure properly I will be in a position to screw them into place again.

Oakey Dokey

I’ve decided to build the hull in the same way the B&B video recommends, i.e. use the bunk sides as references for the frame locations, but also to keep the bunk sides in place going forward with the build. – they add good reference points and stiffness to the structure while half-completed. To do this all the floors need to be in place at the planking stage as they cannot be fitted with the bunk sides in place.

There are some templates available for the floors – getting actual PDFs of all the B&B drawings is not straightforward – a single pack with a schedule would be nice, but the kit isn’t really at this stage yet. Either way, i got hold of them from Fyne and printed them out at 100% onto many sheets of A4, then stuck them together to make the full size patterns.

The oak planks I got from Robbins timber down in Bristol – almost, but not quite good service from these guys. The material is ok, the service on site grumpy and slow. A work trip to this area allowed me to drop in and bring the wood back in the car while MegaCorp paid my mileage…

The timber is rough sawn at 65mm thick, chopping this up on the bandsaw and thicknessing with the sled was straightforward enough to get hte 60x70mm profiles. Using the templates I cut them to size on the bandsaw and chiselled out the notches. The notches on the templates are minimum size guides, so will need a bit of adjustment once offered up to the stringers, getting most of the material out now is a bonus though.

After rounding over with the usual router bit they dropped into place on the bunk sides perfectly. Another job done.

In the mean time i scarfed all the stringers and am now offering them up to the frames for bevelling the notches…

Its starting to look quite boat-like now.

Onwards.

The ScarfMaster and frames on the jig.

I’m finally done with making the frames on the bench which is a nice feeling. Onward up to the cow shed and the build continues there.

The uprights for the jig went on pretty easily, using a laser level, set square and a number of tape measures to ensure trueness of every upright. I’d previously drawn on the water lines onto the frames, so levelling these with the laser level using the water lines was pretty straightforward. I added some temporary marker plates to the transom frame as the waterline is 10mm above (i.e. below when right way up) the transom bottom chine, this allowed me to use this to square this frame up like the rest with the laser level (as it allowed the laser line to reflect off something…).

I’d previously glued up the bunk sides (they are in two pieces with a butt block), these slotted into place easily and the other frames simply slotted onto these. I also screwed in some support blocks for the bottom of these frames so they don’t wiggle about too much. This isn’t indicated on the jig drawings, but i think will help at stringer time.

The stem is a bit of a pain in the arse to setup, but after some shoddy carpentry and the laser level again it is in place, accurate and rigid enough to take the stringers being clamped to it. Checking the fairness of the stem knee and the bunk sides, everything looks pretty good.

I have no idea how boatbuilders were so accurate before CNC machines, laser levels and power tools…

On to stringers – I used ‘The Bodgers Friend’ (AKA the pocket hole jig) to create a simple aid to cut the scarfs. Nothing too clever, just a 1:10 saw guide that is perfectly perpendicular. (for the 22mm dimension of the stringers) This seems to work pretty well and the next job is to cut scarfs on all the stringers that I thicknessed down to the right dimensions the other evening. The notches on the frames are actually 31 (and a bit) mm wide x 22mm, so a 30 x 22mm stinger is a pretty loose fit. I made my stringers a bit tighter tolerance, but this might come back to bite me later when i come to fit them…

In a side note: I’m pretty pleased with the thicknesser. I can buy rough sawn planks at a dramatically cheap cost per cuft, and using either the circular saw or the bandsaw rip them down and thickness them to the correct size. I estimate that it has paid for itself at least once so far judging by the advertised per metre costs of planed finish Douglas Fir that i looked at originally.