Ply planking

Got a few updates from the yard – loads of progress on the boat! I’ve been traveling around a bit these last few weeks and haven’t had a chance to update the blog. MegaCorp™ seem happy with the last project I’ve done and have moved me onto a load more… More hotels and more planes and trains etc.

 

The cockpit coaming:

The new cockpit coaming has been laminated up and fitted along with a new carlin down the side of the cockpit. The guys at the yard decided to change the way the coaming mounts to the side of the coachroof and have created a stronger join – looks ok too.

 

The deck:

The foredeck ply went down, then I got an update a week and a half later that the rest was almost done. Both layers of the ply are screwed to each other and the deck beams. The underside of the foredeck section has had grooves routed into it to replicate a kind of planked effect. Two layers of 12mm ply should be adequate strength-wise…

 

The coachroof:

The ply around the two portholes where the surveyor found the rot have been uncovered and quantities of a kind of compost removed. Lovely.

New ply will be scarfed into place to repair the sections.