Where has the summer gone?

So, while the blog has been quiet, the workshop hasn’t.

The windows went in, 10mm polycarbonate, shaped to fit the recesses. Overkill, yep (as usual), but makes them flush to the hull sides.

Started working on the stainless steel items. This took ages. The thin wall stainless kicked my ass for a while before some new equipment and better technique got me some acceptable welds. I am far from being a good welder though, so they aren’t perfect, but they are sevicable and have saved me a fortune in costs if someone else did the work for me.

I added all the glassfibre rod pieces into place where the deck hardware is to be. About 300 odd holes… its a long process but should ensure the plywood stays totally encapsulated in resin and glass.

The topsides paint finish was not as good as I hoped, so pinholes were filled and another 3 coats of polyurethane were applied to the outside. 2 coats of epoxy primer and a topcoat of matt PU was applied inside as well. This was not a pleasant job, but using a full face mask with 3M filters for paint fumes it was OK. (I forget the code, but they were very effective, I couldn’t even smell the PU in the mask). I then added all the premade locker doors inside with latches etc.

Finally finished the daggerboards and rudder and tiller. These had been collecting dust in a half finished state for months. Good to get stuff actually completed.

Built the keel bulb mould from the 3D printed pattern made months ago. It was basically concrete in a plywood box. I added a further 20mm to the mould height as a few builders reported light bulbs when poured to the plans.

I took the mould to ‘Sandcast Lead Ltd’ in Leicester. Kelvin, the very knowledgeable and super helpful owner ensured I got the bulbs poured perfectly. He had the lead pot on before I got there, we poured the lead and let it cool, turned out the mould (the additional 20mm of mould fell off at this point but we didn’t need it, as the lead was so pure) and did the second one, all in about 4 hours. We used their industrial scales to pour in exactly 75kgs of lead, which allowed for a bit extra to fair and trim them to size. I drove home a very happy man with two very hot lead bulb halves in the boot of the car.

Then came a bunch of small jobs, all taking time, but the boat was really starting to come together.

The solar panel mounts are glassfibre panels and tubes strengthened to take a windsurf universal joint. The panels themselves are sikaflexed and bolted to aluminium ‘x’ shapes with strengthening where the UJ mounts.

All the stainless was polished and mounted, and stuff like dagger boards and rudder hinges went on. I added the compulsory hi viz to the sheer strake panel with vinyl, and fitted various bits of deck hardware in the locations where the glassfibre tube had been glued in.

I also smashed out a sprayhood on the sewing machine that covers the hatch way with a glassfibre cowl that it attaches to. It’s a bit baggy maybe, but does the job.

Guardrails then went on. (They are a bit of a nod to safety only, but are as per plans. They don’t provide much guarding at all).

Then the lead was planed to smooth on the inside and down to weight, then drilled to take the bolts by using the keel as a template so the holes were precise.

The mast was still stuck in transit at this point, and stayed like that for 4 weeks, so I made the outside handles for the main hatch and a few other bits and bobs while also wiring the boat up fully. And then, it was done! Off to Scotland for the first sail!